Planning a trail work weekend to replace the Kickapoo Up board walks. Will be working both days to try to get it completed in a single weekend. If you can please post up if you plan to attend one or both days as this will help us plan work accordingly.
The boardwalks on Kickapoo Up have seen better days and we are going to rebuild them entirely. We will start by tearing out the old boardwalks (there will be a dumpster on site) and then rebuilding from the ground up as much of the existing structured is quite deteriorated. We are planning consecutive trail days to try and get this knocked out in a single weekend and minimize trail traffic disruptions. We will need people to help haul the existing materials down as well had transport new materials. We will have tools on hand but below if a list of items that would be helpful to bring.
-Flat bars/pry bars
-Impact drivers
-Circular saws (battery operated is best)
-Tape measures
-Speed squares
-Wheel barrows